Timeline
April 15, 2008-Pour Slab On Grade
April 21, 2008-Building Steel Delivered
May 2, 2008-Koreteck Panel Delivery
May 5, 2008-Building Steel Pass Inspection
May 5, 2008 Begin Stand Koreteck Panel
May 13, 2008-Exterior Panel Install Completed
May 23, 2008-Metal B-Deck Roof Structure Complete
June 13, 2008-Roof Complete
June 16, 2008-Efis Exterior Finish Complete
June 27, 2008-Storefront Complete
July 28, 2008-Building Complete (Mechanical, Electrical, Plumbing)
Project Type
Steel Structure with Koreteck High Density Reinforced Foam Exterior Walls
Design-Build
Square Footage
24,000 sq. ft.
Exterior Finish
Three (3) coat integral color Efis system
Stone accents at the Storefront System
Roof
Two (2) three (3) inch layers of High Density Foam
Four Ply Sheeting
Lighting
Twenty-Eight (28) Two (2) Light Custom Exterior Wall Sconces
Storefront
One (1) inch Solarban 60 Glass in Extruded Aluminum Storefront System